Road No. |
District |
Start-End Km |
Stations |
EAADT |
SUMMARISED RECOMMENDATIONS |
D2863 |
Tsumeb |
29,4 33,3 |
(Kombat)-Reg.Border-D3022 |
35 |
Road is maintained by Otjozondjupa Region |
D3001 |
Tsumeb |
0,0 19,0 |
T0110 (south of Oshivelo)-D3004 |
7 |
Maintenance level of grading every third week
has to be reduced to six times per year |
D3001 |
Tsumeb |
19,0 40,7 |
D3004-D3007 |
7 |
Maintenance level of grading every third week
has to be reduced to six times per year |
D3001 |
Tsumeb |
40,7 58,4 |
D3007-D3047 |
7 |
Maintenance level of grading every third week
has to be reduced to six times per year |
D3001 |
Tsumeb |
58,4 79,6 |
D3047-M0075 (south Tsintsabis) |
7 |
Maintenance level of grading every third week
has to be reduced to six times per year |
D3003 |
Tsumeb |
0,0 27,8 |
T0110-D3028 |
5 |
Maintenance level of grading every three
months has to be reduced to two times per year. Proclamation to a Farm Road has to be
considered |
D3004 |
Tsumeb |
0,0 20,9 |
T0110-D3001 |
4 |
Maintenance level of grading every three
months has to be reduced to two times per year. Proclamation to a Farm Road has to be
considered |
D3007 |
Tsumeb |
0,0 54,4 |
T0110 (north of Tsumeb)-D3001 |
8 |
Maintenance level is appropriate |
D3016 |
Tsumeb |
0,0 18,1 |
M0075 (Tsintsabis)-D3017 |
4 |
Maintenance level of grading every three
months has to be reduced to two times per year. Proclamation to a Farm Road has to be
considered |
D3016 |
Tsumeb |
18,1 25,0 |
D3017-Reg.Border (Otjozondjupa) |
4 |
Maintenance level of grading every three
months has to be reduced to two times per year. Proclamation to a Farm Road has to be
considered |
D3017 |
Tsumeb |
39,3 53,6 |
(Abenab)-Reg.Border (Otjozondjupa)-D3016 |
15 |
The Routine Maintenance and blading frequency
of 4 times per year (table 22) is appropriate and should be sustained. Shrubs on the
shoulders should be removed |
D3021 |
Tsumeb |
0,0 14,5 |
M0072-Reg.Border-(Otjozondjupa) |
6 |
Road is maintained by Otjozondjupa Region |
D3022 |
Tsumeb |
13,4 27,2 |
(M0072)-Reg.Border (Otjozondjupa)-D2863 |
25 |
Road is maintained by Otjozondjupa Region |
D3022 |
Tsumeb |
27.2 41,4 |
D2863-Reg.Border (Otjozondjupa)-(T0082) |
25 |
Road is maintained by Otjozondjupa Region |
D3025 |
Tsumeb |
0,0 47,8 |
D3028- Reg.Border (Otjozondjupa) |
1 |
Proclamation to a Farm Road has to be
considered (Is in the process to be deproclaimed as a district road) |
D3028 |
Tsumeb |
64,0 90,7 |
(Otavi)-Reg.Border (Otjozondjupa)-D3025 |
3 |
Maintenance level of grading every three
months has to be reduced to once a year. Proclamation to a Farm Road has to be
considered |
D3028 |
Tsumeb |
90,7 93,3 |
D3025-D3003 |
3 |
Maintenance level of grading every three
months has to be reduced to once a year. Proclamation to a Farm Road has to be
considered |
D3028 |
Tsumeb |
93,3 113,0 |
D3003-M0084 |
3 |
Maintenance level of grading every three
months has to be reduced to once a year. Proclamation to a Farm Road has to be
considered |
D3031 |
Tsumeb |
48,3 56,4 |
(Otavi)-Reg.Border (Otjozondjupa)-D3022 |
5 |
Road is maintained by Otjozondjupa Region |
D3039 |
Tsumeb |
0,0 20,6 |
M0075-Reg.Border (Otjozondjupa) |
2 |
Maintenance level of grading every three
months has to be reduced to once a year. Proclamation to a Farm Road has to be
considered |
D3043 |
Tsumeb |
0,0 19,4 |
T0110-D3031 |
13 |
Maintenance level of grading every two weeks
has to be reduced to 12 times per year. |
D3043 |
Tsumeb |
19,4 24,1 |
D3031- Reg.Border (Otjozondjupa)-(D3028) |
13 |
Maintenance level of grading every two weeks
has to be reduced to 12 times per year. |
D3047 |
Tsumeb |
0,0 42,5 |
M0075 (north of Tsumeb)-D3001 (west of
Tsintsabis) |
4 |
Maintenance level of grading every fifth week
has to be reduced to twice a year. Proclamation to a Farm Road has to be considered |
D3600 |
Tsumeb |
0,0 13,3 |
M0075/D3016 (Tsintsabis)-Reg.Border
(Ohangwena) |
2 |
Has to be constructed according to the
priorities of the revised Ovamboland Road Master Plan |
D3602 |
Tsumeb |
50.6 57,3 |
Reg.Border (Ohangwena)-D3603 (Okankolo) |
37 |
The Routine Maintenance and blading frequency
of 15 times per year (table 22) is appropriate and should be sustained. |
D3603 |
Tsumeb |
0,0 31,2 |
T0111 (Onathinge)-D3602 (Okankolo) |
59 |
The Routine Maintenance and blading frequency
of 15 times per year (table 22) is appropriate and should be sustained. Medium term
paving has to be considered if the section of D3603 reaches an AADT of 70. |
D3603 |
Tsumeb |
31,2 40,4 |
D3602 (Okankolo)-D3631 |
59 |
The Routine Maintenance and blading frequency
of 15 times per year (table 22) is appropriate and should be sustained. Medium term
paving has to be considered if the section of D3603 reaches an AADT of 70. |
D3603 |
Tsumeb |
40,4 91,9 |
D3631-D3630 (Ohumbula) |
4 |
Has to be constructed according to the
priorities of the revised Ovamboland Road Master Plan |
D3603 |
Tsumeb |
91,9 132,9 |
D3630 (Ohumbula) -Reg.Border
(Ohangwena)-(Okongo) |
4 |
Has to be constructed according to the
priorities of the revised Ovamboland Road Master Plan |
D3606 |
Tsumeb |
6,7 11,1 |
Reg.Border (Oshana)-D3629 (west of Olukonda) |
16 |
Traffic counts to be verified. Re-gravelling
is recommended and maintenance by appropriate L.B. maintenance techniques based on
community participation have to be sustained. A blading frequency of 24 times per year is
regarded too high for an AADT=16 (table 22).
Medium term paving has to be considered if the section of D3606 reaches an AADT of 70. |
D3625 |
Tsumeb |
24,7 31,1 |
Reg.Border (Ohangwena) Begin
of Seal |
19 |
Traffic counts to be verified. A
blading frequency of 24 times per year is possibly too high for an AADT=19 (table 22). |
D3625 |
Tsumeb |
31,1 31,4 |
Begin of Seal- M0121 (east of Oshigambo) |
19 |
Traffic counts to be verified. A blading
frequency of 24 times per year is possibly too high for an AADT=19 (table 22). |
D3629 |
Tsumeb |
0,0 3,4 |
T0111 (Onethindi)-D3606 (Olukonda) |
31 |
Traffic counts to be verified. With a
possible traffic load of AADT> 100 this section has to be upgraded to a paved single
surfacing layer as top priority.
E.Q. blading with a blading frequency of 52 times (table 22) per year is not
sufficient. |
D3629 |
Tsumeb |
3,4 5,8 |
D3606 (Olukonda)-Okaloko |
22 |
Re-gravelling is recommended and maintenance
by appropriate L.B. maintenance techniques based on community participation have to be
sustained. A blading frequency of 24 times per year is regarded too high for an AADT=16
(table 22). Medium term paving has to be considered if the section of D3629 reaches an
AADT of 70. |
D3630 |
Tsumeb |
0,0 13,1 |
T0111 (Onyati)-D3631 (Onyuulaye) |
34 |
The Routine Maintenance and blading frequency
of 24 times per year (table 22) is appropriate and should be sustained. |
D3630 |
Tsumeb |
13,1 80,0 |
D3631 (Onyuulaye)-D3603 (Ohumbula |
9 |
The Routine Maintenance and blading frequency
of 24 times per year (table 22) is appropriate and should be sustained because it can be
expected that with the completion of the construction the traffic will increase. |
D3631 |
Tsumeb |
0,0 20,5 |
D3603 (east of Okankolo)-D3630 (Onyuulaye) |
10 |
The Routine Maintenance and blading frequency
of 24 times per year (table 22) is appropriate and should be sustained because it can be
expected that the traffic will increase. |
M0075 |
Tsumeb |
11,6 21,2 |
End of seal-D3047 |
79 |
The Routine Maintenance and blading frequency
of 24 times per year (table 22) is presently appropriate. Medium term paving has to be
considered if M0075 reaches an AADT of between 100 and 120 (table 29). |
M0075 |
Tsumeb |
21,2 27,9 |
D3047-D3039 |
79 |
The Routine Maintenance and blading frequency
of 24 times per year (table 22) is presently appropriate. Medium term paving has to be
considered if M0075 reaches an AADT of between 100 and 120 (table 29). |
M0075 |
Tsumeb |
27,9 61,1 |
D3039-D3001 |
79 |
The Routine Maintenance and blading frequency
of 24 times per year (table 22) is presently appropriate. Medium term paving has to be
considered if M0075 reaches an AADT of between 100 and 120 (table 29). |
M0075 |
Tsumeb |
61,1 65,0 |
D3001-D3016 (Tsintsabis) |
79 |
The Routine Maintenance and blading frequency
of 24 times per year (table 22) is presently appropriate. Medium term paving has to be
considered if M0075 reaches an AADT of between 100 and 120 (table 29). |
M0075 |
Tsumeb |
65,0 65,2 |
D3016 (Tsintsabis)-D3600 |
79 |
The Routine Maintenance and blading frequency
of 24 times per year (table 22) is presently appropriate. Medium term paving has to be
considered if M0075 reaches an AADT of between 100 and 120 (table 29). |
M0121 |
Tsumeb |
21,6 23,4 |
End of Seal-Reg.Border (Ohangwena) |
525 |
With a traffic load of AADT> 500 this
section has to be urgently upgraded to a paved single surfacing layer (or even higher) as
a short to medium term priority (L.B. construction). E.Q. blading with a blading
frequency of 52 times (table 22) per year is not sufficient.
Under the peculiar existing wearing course materials situation re-gravelling will
not result in a stable maintenance level and valuable basecourse and subbase materials
will be wasted. |